Additional works. ECJ 2013 judgments

Podobné dokumenty
Tento materiál byl vytvořen v rámci projektu Operačního programu Vzdělávání pro konkurenceschopnost.

GUIDELINES FOR CONNECTION TO FTP SERVER TO TRANSFER PRINTING DATA

Litosil - application

AIC ČESKÁ REPUBLIKA CZECH REPUBLIC

Introduction to MS Dynamics NAV

USING VIDEO IN PRE-SET AND IN-SET TEACHER TRAINING

Theme 6. Money Grammar: word order; questions

ESPD & e-certis support on the way o once-only principle in e-procurement

Vánoční sety Christmas sets

Národní informační den společných technologických iniciativ ARTEMIS a ENIAC

Contact person: Stanislav Bujnovský,

SECTION BLOCK 3. Risks in auditing with regard to the tendering process. Břetislav GRÉGR. 24th April, 2015, Budapest

Fytomineral. Inovace Innovations. Energy News 04/2008

Role DSO v implementaci GDPR

VY_32_INOVACE_06_Předpřítomný čas_03. Škola: Základní škola Slušovice, okres Zlín, příspěvková organizace

PRODEJNÍ EAUKCE A JEJICH ROSTOUCÍ SEX-APPEAL SELLING EAUCTIONS AND THEIR GROWING APPEAL

Transportation Problem

FIRE INVESTIGATION. Střední průmyslová škola Hranice. Mgr. Radka Vorlová. 19_Fire investigation CZ.1.07/1.5.00/

WORKSHEET 1: LINEAR EQUATION 1

Czech Republic. EDUCAnet. Střední odborná škola Pardubice, s.r.o.

Gymnázium, Brno, Slovanské nám. 7 WORKBOOK. Mathematics. Teacher: Student:

The Military Technical Institute

Střední průmyslová škola strojnická Olomouc, tř.17. listopadu 49

Ministerstvo školství, mládeže a tělovýchovy Karmelitská 7, Praha 1 tel.: msmt@msmt.cz

Publish date 9/13/2013 4:22 AM. Bid due date 11/4/ :00 AM. Change date 9/13/2013 4:22 AM

PÍSEMNÁ ZPRÁVA ZADAVATELE K VEŘEJNÉ ZAKÁZCE / THE WRITTEN REPORT OF THE CONTRACTING ENTITY TO THE TENDER PROCEDURE

Škola: Střední škola obchodní, České Budějovice, Husova 9. Inovace a zkvalitnění výuky prostřednictvím ICT

SMES-EU D&H-5P Workshop 1. Prague November 2003 V Praze listopadu 2003

/ 1. I nadále budeme vyhledávat možnosti uplatnění na zahraničních aktivitách, kde jsme v předešlých letech načerpali dostatek zkušeností

Mechanika Teplice, výrobní družstvo, závod Děčín TACHOGRAFY. Číslo Servisní Informace Mechanika:

Zelené potraviny v nových obalech Green foods in a new packaging

ActiPack rozšířil výrobu i své prostory EMBAX Od ledna 2015 jsme vyrobili přes lahviček či kelímků. Děkujeme za Vaši důvěru!

VYSOKÁ ŠKOLA HOTELOVÁ V PRAZE 8, SPOL. S R. O.

Aktuální situace mezi novináři v České Republice Present situation of journalism in the Czech Republic

Byznys a obchodní záležitosti

Property insurance services

Publish date 12/27/2012 4:24 AM. Bid due date 3/4/ :00 AM. Change date 12/27/2012 4:24 AM

Publish date 6/23/2012 4:23 AM. Bid due date 7/23/ :00 AM. Change date 6/23/2012 4:23 AM

DC circuits with a single source

Projekt: ŠKOLA RADOSTI, ŠKOLA KVALITY Registrační číslo projektu: CZ.1.07/1.4.00/ EU PENÍZE ŠKOLÁM

Program CIP ICT PSP 5. výzva 2011

Tabulka 1 Stav členské základny SK Praga Vysočany k roku 2015 Tabulka 2 Výše členských příspěvků v SK Praga Vysočany Tabulka 3 Přehled finanční

IPR v H2020. Matěj Myška myska@ctt.muni.cz

Invitation to ON-ARRIVAL TRAINING COURSE for EVS volunteers

SPECIFICATION FOR ALDER LED

User manual SŘHV Online WEB interface for CUSTOMERS June 2017 version 14 VÍTKOVICE STEEL, a.s. vitkovicesteel.com

Příručka ke směrnici 89/106/EHS o stavebních výrobcích / Příloha III - Rozhodnutí Komise

CZ.1.07/1.5.00/

EXACT DS OFFICE. The best lens for office work

Projekty v Turecku financované z předvstupních evropských fondů Miroslav Kelnar CzechTrade Istanbul

Číslo projektu: CZ.1.07/1.5.00/ Název projektu: Inovace a individualizace výuky

COUNCIL OF THE EUROPEAN UNION. Brussels, 17 January /05 COPEN 9 EJN 1 EUROJUST 1

Water Planning in the Czech Republic

Ustav struktury a mechaniky hornin AVCR, Ie: se sidlem V Holesovickich 94/41, Praha 8 Zastoupen: RNDr. Josef Stemberk

PROHLÁŠENÍ O VLASTNOSTECH

Výukový materiál zpracovaný v rámci operačního programu Vzdělávání pro konkurenceschopnost

CENTRAL GOVERNMENT AUTHORITIES 1

Postup objednávky Microsoft Action Pack Subscription

Caroline Glendinning Jenni Brooks Kate Gridley. Social Policy Research Unit University of York

Why PRIME? 20 years of Erasmus Programme Over 2 million students in total Annually

Právní formy podnikání v ČR

I N F O R M A T I O N

Příručka ke směrnici 89/106/EHS o stavebních výrobcích / Příloha III - Rozhodnutí Komise

PRAVIDLA ZPRACOVÁNÍ STANDARDNÍCH ELEKTRONICKÝCH ZAHRANIČNÍCH PLATEBNÍCH PŘÍKAZŮ STANDARD ELECTRONIC FOREIGN PAYMENT ORDERS PROCESSING RULES

Case Study Czech Republic Use of context data for different evaluation activities

GENERAL INFORMATION MATCH: ALSA PRO HOT SHOTS 2018 DATE:

GENERAL INFORMATION MATCH: ALSA PRO ARENA MASTERS DATE: TIME SCHEDULE:

Výukový materiál v rámci projektu OPVK 1.5 Peníze středním školám

Britské společenství národů. Historie Spojeného království Velké Británie a Severního Irska ročník gymnázia (vyšší stupeň)

Cambridge International Examinations Cambridge International General Certificate of Secondary Education

PART 2 - SPECIAL WHOLESALE OFFER OF PLANTS SPRING 2016 NEWS MAY 2016 SUCCULENT SPECIAL WHOLESALE ASSORTMENT

Hodnocení nejen na cenu praktické zkušenosti

B1 MORE THAN THE CITY

Enabling Intelligent Buildings via Smart Sensor Network & Smart Lighting

Zpráva o právních aspektech energetické účinnosti v textilním průmyslu

Medical equipments. Info. Buyer. Version changes Contract notice. Version 2. Publish date 11/21/2014 4:13 AM. Bid due date 12/11/ :30 AM

Číslo projektu: CZ.1.07/1.5.00/ Název projektu: Inovace a individualizace výuky

PROHLÁŠENÍ O VLASTNOSTECH. DoP: pro fischer RM II (Lepená kotva pro použití v eto u) CS

The Over-Head Cam (OHC) Valve Train Computer Model

Press book English Language

Cambridge International Examinations Cambridge International General Certificate of Secondary Education

SEZNAM PŘÍLOH. Příloha 1 Dotazník Tartu, Estonsko (anglická verze) Příloha 2 Dotazník Praha, ČR (česká verze)... 91

Střední průmyslová škola strojnická Olomouc, tř.17. listopadu 49

Příručka ke směrnici 89/106/EHS o stavebních výrobcích / Příloha III - Rozhodnutí Komise

Střední odborná škola stavební a Střední odborné učiliště stavební Rybitví

Immigration Studying. Studying - University. Stating that you want to enroll. Stating that you want to apply for a course.

Immigration Studying. Studying - University. Stating that you want to enroll. Stating that you want to apply for a course.

PAINTING SCHEMES CATALOGUE 2012

Příručka ke směrnici 89/106/EHS o stavebních výrobcích / Příloha III - Rozhodnutí Komise

Publish date 8/17/2013 4:13 AM. Change date 8/17/2013 4:13 AM

Travelling Rules for Inbounds in District 2240 Czechia and Slovakia

Stojan pro vrtačku plošných spojů

PROHLÁŠENÍ O VLASTNOSTECH. č CS

GENERAL INFORMATION MATCH: ALSA PRO OPEN 2018 DATE: TIME SCHEDULE: Prematch - Friday. registration:

Instrukce: Cvičný test má celkem 3 části, čas určený pro tyto části je 20 minut. 1. Reading = 6 bodů 2. Use of English = 14 bodů 3.

Air Quality Improvement Plans 2019 update Analytical part. Ondřej Vlček, Jana Ďoubalová, Zdeňka Chromcová, Hana Škáchová

Education and training services

Digitální učební materiál

Klepnutím lze upravit styl Click to edit Master title style předlohy nadpisů.

Vypsání závodu / Notice of Race strana/page 1/5. Compotech Cup. v lodních třídách / in classes. D-One, 7P CTL

Transkript:

Additional works ECJ 2013 judgments Rafael López Sánchez Directorate-General Directorate C Audit Praha, 11 April 2013

Outline Legislative framework Why "additional works" are important? DG REGIO approach Recent ECJ judgments Main conclusions 2

Legislative framework Directive 2004/18/EC of 31 March 2004 on the coordination of procedures for the award of public works contracts, public supply contracts and public service contracts Directive 2004/17/EC of 31 March 2004 coordinating the procurement procedures of entities in the water, energy, transport and postal services sectors EU Treaty ECJ case law National laws on public procurement 3

Additional works legal framework Article 31.4(a) of the Directive 2004/18/EC Article 40.3(f) of the Directive 2004/17/EC (sectors of water, energy, transport and postal services) Maintain principles already established in previous Directives (92/50,93/37,93/38) 4

Legislative framework GOLDEN RULE The procedure to be used are the open and the restricted procedures The negotiated procedure without publicity can only be used in a very exceptional cases Please bear in mind this golden rule when you start to prepare the tendering procedures. Any deviation of this rule will need many justifications and may trigger financial corrections 5

Why additional works are important? Considering all the irregularities detected by DG REGIO since 2005 on both programming periods (2000-2006 and 2007-2013) the weight of the Public Procurement is about 40% in each period. The use of negotiated procedure to award additional works represents aprox. 25% of the Public Procurement irregularities. If we avoid this practice, the error rate will be reduced ECA audits have arrived to similar conclusions. In DAS 2009, the 75% of quantified errors were due to non-compliance with Public Procurement rules 6

DG REGIO approach - -Directives and ECJ case law are rather clear but national legislations should be compatible with the EC legal framework. Many problems in the past were due to wrong transpositions. In this respect, the lead services in the Commission is DG MARKT -Negotiated procedure without publicity is an exceptional procedure and needs justifications case by case. Very important: The burden of proving the actual existence of exceptional circumstances justifying a derogation lies on the one seeking to rely on those circumstances -They cannot be accepted as unforeseen circumstances those events that a diligent contracting authority acting in the normal course of business should have foreseen 7

DG REGIO approach - The justifications to use a negotiated procedure should be well-kept in the tendering file since the beginning and cannot be added afterwards - In case of lack of proper evidence, DG REGIO will always apply a financial correction following the COCOF guidelines - For info: DG REGIO has already applied financial corrections to many Member States ( from south to north, east to west) due to lack of justifications/ evidences of the use of negotiated procedure to award additional works. 8

Main DG REGIO findings Additional works Implementation of contracts / Modifications a) Additional works or services directly awarded to the economic operator in place, when amount exceeds 50% of the amount of original contract, the circumstances invoked are not unforeseen even if circumstances are unforeseen, when works/services are economically or technically separable b) Automatic extension of supervision contracts because of delays in the execution of works contracts 9

Main DG REGIO findings Additional works a) Additional works not included in the project initially considered or in the original contract I. Tender documents should be the result of careful planning and include all necessary elements for a genuine competition II. «Unforeseen» events should be interpreted in an objective manner as referred to what the authorities should have foreseen and not to what they actually did III. Consider the means available to the contracting authority, the characteristics of the project and the good practices in the field 10

European Court of Justice Previous Case Law Strict interpretation of the exceptions to use negotiated procedure C-199/85 Commission/Italy paragraph 14 C-57/94 Commission/Italy paragraph 23 C-318/94 Commission/Italy paragraph 14 C-187/04 Commission/Italy paragraph 24 C-84/03 Commission/Spain paragraphs 46/48/50 11

European Court of Justice Previous Case Law Modifications of contracts / Substantial character C-496/99 Succhi di Frutta paragraphs 117/118 C-454/06 Pressetext paragraphs 34/36 All mentioned judgements are available following the link: http://curia.europa.eu/jcms/jcms/j_6/ 12

European Court of Justice New Cases 2013 On 31/01/2013, the General Court rendered two judgments in cases T-540/10 and T-235/11 both Commission/Spain. These 2 judgments are only available in French ( procedure language) and Spanish (Member State language). No guarantee that they will be translated to all languages The cases related to direct award of a number of additional contracts for the construction of the High Speed Railway (AVE) in Catalonia and Castilla-La Mancha co-financed by the Cohesion Fund. Spain attacked the Commission's decisions to impose a financial correction for using, without a legal basis, negotiated procedures without prior publication of tender notices instead of correctly procuring the contracts 13

European Court of Justice New Cases 2013 ECJ stressed that the exceptions to use the negotiated procedure have to be interpreted in a strict manner, taking into account that the contracting entity must prove that it acted in a diligent way 14

European Court of Justice New Cases 2013 Different circumstances invoked by the contracting authority and not accepted by DG REGIO ( confirmed by ECJ): 1.- Circumstances concerning urban planning As a general rule, the contracting entity must, in cases in which other public entities are competent to define, according to national legislation, this urban planning, seek an agreement with these public entities before launching the tendering procedure in order to avoid modifications of the initial project in the phase of works execution 15

European Court of Justice New Cases 2013 2.- Circumstances concerning late requests from public or private entities The same principle applies to the environmental evaluation of the project. The contracting entity must prove that it had consulted these entities before launching the tendering procedure. If this consultation has not taken place, requests made by public or private entities after the publication of the tender notice in the OJEU are not to be considered, per se, as an unforeseen circumstance 16

European Court of Justice New Cases 2013 3.- Geological reasons The contracting entity must conduct sufficient geological surveys in order to obtain an in-depth knowledge of the geological conditions of the area affected by the infrastructure. These surveys have to be conducted before launching the tendering procedure. Concerning the level of diligence required, the General Court indicated that the contracting authority must take into account the available technical data before launching the tendering procedure and the foreseeable evolution of these data (geological, demographical, socio-economical ) according to the duration of the execution of works in order to prepare the initial project 17

European Court of Justice New Cases 2013 Some interesting points of the judgments: Case T-235/11 (paragraph 101): The contracting authority has to ensure a level of quality of the initial project and adopt measures during the planning phase of the contract in order to minimise the risk Case T-235/11 (paragraphs 88 to 94): requirements of other administrations ( at higher or different level) cannot be assessed as unforeseen circumstances as the contracting authority should act in a diligent way during the planning phase Case T-235/11 (paragraph 105): the simple extension of a work contract is not enough justification to extend the services contract through direct award 18

European Court of Justice New Cases 2013 Case T-540/10 (paragraph 83): a diligent contracting authority should take into account reasonably the potential social-economic and demographic evolution of the affected areas Case T-540/10 (paragraph 90): it was obligation of the contracting authority acting in a diligent way to ensure prior agreements with the different municipalities affected by the works. These agreements have to be done before the publication of the contract notice (paragraph 85 of case T-235/11) 19

Questions from CZ authorities (1) doměrky u některých položek (např. zemní práce) není reálně možné předem přesně stanovit objemy prací. Je nutné stanovit postup pro posuzování oprávněnosti těchto víceprací, příp. omezit procentuálně, a dále stanovit, zda se tyto vícepráce započítávají do limitu 20%. Additional measured quantities for some items (e.g. earthworks), it is not possible in reality to specify the exact volume of works in advance. It is necessary to set up a procedure for assessing the legitimacy of these extra works, or limit these by a percentage of the total, and also specify whether these extra works fall into the 20% limit. 20

Questions from CZ authorities (2) vícepráce, jejichž potřeba se zjistila až po ukončení výběrového řízení či podpisu smlouvy s vybraným zhotovitelem, jsou pro nezbytné pro úspěšné dokončení díla, ale jedná se zejména o opomenutí investora/projektanta při přípravě zadávací dokumentace. Vzhledem k tomu, že projektant je ve většině případů externí společnost, bylo by možné považovat tyto vícepráce za nepředvídatelné při současném uplatnění záruky za vady díla na příslušném projektantovi? Dovoluji si podotknout, že případné vyhlášení samostatného otevřeného výběrového řízení by naráželo na princip řádného hospodáře, protože stavba samotná by musela být zastavena a zakonzervována, což by přineslo značné dodatečné náklady, jejichž zadání by rovněž bylo problematické Extra works that were identified only after completion of the tender or signature of the contract with the selected contractor and that are necessary for a successful completion of the work, but are caused mostly by negligence/omission on the side of the investor/designer when preparing the terms of reference for the tender. As detailed design is usually performed by an external company, would it be possible to consider these extra works as unpredictable while claiming at the same time warranty for defects of work from the designer in question? It must be noted that a possible launching of a new tender would be contrary to the principle of due diligence and care as the construction itself would have to be stopped and preservation measures applied to construction site. This would lead to substantial additional costs while the tendering of these works would also be problematic. 21

Questions from CZ authorities (3) vícepráce, které vzniknou z důvodu rozdílu mezi výkresovou částí projektové dokumentace a výkazem výměr (součást zadávacích podmínek pro výběrové řízení)? Extra works caused by difference between the detailed design drawings from project documentation and the bill of quantities (part of terms of reference for the tender)? 22

Questions from CZ authorities (4) odpovědnostní závazky jedná se o závazky, které vzniknou pochybením na straně zadavatele, např. pozdní předání staveniště. Smlouvy o dílo s tímto počítají a obsahují i ustanovení pro výpočet takto vzniklých nákladů. Může toto být zahrnuto mezi způsobilé výdaje? Liabilities resulting from duties and responsibilities these would be liabilities caused by fault on the side on the contracting authority, for example delay in handing over of the construction site. Can this be included in eligible expenditure? 23

Questions from CZ authorities (5) návrhy úsporných opatření ustanovení FIDIC (Red Book) počítají s tím, že zhotovitel může podat návrh na změnu, která má přinést úsporu nákladů, a dokonce mu za to přísluší část takto uspořených prostředků. Je vůbec možné při současném striktním výkladu zadávání veřejných zakázek tento institut využít Proposed saving measures according to FIDIC rules (Red Book), the contractor may propose a variation that would lead to cost reduction and should be rewarded by a part of the resources thus saved. Is it even possible to apply this mechanism at all taking into account the current strict interpretation of public procurement? 24

Questions from CZ authorities (6) nové technologické postupy či materiály dojde-li od doby schválení projektové dokumentace ke kvalitativní změně v oblasti technologických postupů či stavebních materiálů (případně jsou tyto technologie ještě levnější než původní řešení), je možné tyto využít a zadat např. přes JŘBU nebo je nutno striktně realizovat vysoutěžené řešení. Připomínám, že úprava projektové dokumentace je časově náročná záležitost a aktualizace každé z nich před vyhlášením výběrového řízení by tyto stavby zpozdila New technological procedures or materials if a qualitative change in the area of technological procedures or construction materials occurs after the approval of project design documentation (or if these technologies are even cheaper than the original solution), is it possible to use these and procure them using for example the negotiated procedure without publication, or is it necessary to implement strictly the tendered solution? It must be noted that modification of a project design documentation is a rather time consuming activity and updating of each one prior to announcing of tender would delay the constructions in question 25

Questions from CZ authorities (7) sektorový zadavatel byla-li stavba vysoutěžena zadavatelem v pozici veřejného zadavatele a v průběhu realizace stavby došlo ke změně statutu na sektorového zadavatele, je přípustné překročení limitu 20% dodatečných stavebních prací? Sector contracting entity in case the construction was tendered by a contracting entity in the position of a public contracting entity and throughout the construction phase, its status changed to sector contracting entity, is it acceptable to exceed the limit of 20% of additional construction works? 26

Questions from CZ authorities (8) Požadavky nadřízených organizací (např. MD ČR) na úpravu projektu mohou být za nějakých podmínek vyhodnoceny jako nepředvídatelné? Requirements of superior organisations (such as the Ministry of Transport of the Czech Republic) to modify the project can these be under some conditions assessed as unpredictable? 27

Questions from CZ authorities (9) U projektů s historickými objekty se mnohdy naleznou např. zasypané prostory, které vyvolají změnu řešení konstrukce stavebního díla. Často přistupujeme k těmto odůvodněným vícepracem tak, že není dochována relevantní dokumentace objektu a nebylo možné předpokládat tento stav. Postupujeme správně? With projects involving historic buildings, there are often e.g. filled in spaces found, requiring a change in the approach to building construction. We often approach such justified additional work like this: relevant building documentation has not been preserved and such conditions could not be expected. Is our approach correct? 28

Questions from CZ authorities (10) Při realizaci projektů týkající se staveb také řešíme případy, kdy geologický průzkum v rámci projektové přípravy neodhalil skutečnosti, které je pan nutné řešit v průběhu provádění stavby. Např. skalní podloží. V souvislosti s touto skutečností vzniknou vícepráce, jejichž rozsah a způsob postupu prací je řešen na kontrolních dnech. Je možné takto vzniklé náklady považovat za způsobilé? (jsou nám známy podmínky ZVZ, nicméně nás zajímá pohled EK) When implementing projects concerning construction, we also deal with cases where the geological survey performed during project preparation did not find facts that must then be handled during construction, such as bedrock. This is associated with additional work, the scope and method of which is discussed at site meetings. Can such incurred expenditures be considered eligible? (We know the conditions of the Public Contracts Act; nevertheless, we would like to know EC s opinion) 29

Main Conclusions Recent ECJ case law confirms DG REGIO approach on the strict interpretation of the exceptions to use negotiated procedure Borden of proving lies on the Contracting Authority Be aware of the high risk of financial correction 30

Děkuji velmi pěkně Thank you for your attention! Rafael.lopez-sanchez@ec.europa.eu 31